Dickerson Infrastructure repaired approximately 12.61 miles (66,000 LF) of canal banks.
Canal bank repairs included removing existing vegetation, backfilling and compacting the banks to 2.5H:1V slopes (2H:1V slopes with riprap along the south canal bank), installing high-performance turf reinforcement mats on the canal banks for the entire length of the project, sodding, and installing 12-inch diameter HDPE pipes for berm drains.
Project Name
C-41A Canal Bank Stabilization Segment 3, Highlands County, Florida
Owner
South Florida Water Management District
Project Duration
450 days
Construction Completed
May 2013
Project Specs
~12.61 miles (66,000 LF) of canal repair
High-performance turf reinforcement mat installation