C-41A Canal Bank Stabilization

Dickerson Infrastructure repaired approximately 12.61 miles (66,000 LF) of canal banks.

Canal bank repairs included removing existing vegetation, backfilling and compacting the banks to 2.5H:1V slopes (2H:1V slopes with riprap along the south canal bank), installing high-performance turf reinforcement mats on the canal banks for the entire length of the project, sodding, and installing 12-inch diameter HDPE pipes for berm drains.

Project Name

C-41A Canal Bank Stabilization Segment 3, Highlands County, Florida

Project Owner

South Florida Water Management District

Project Duration

450 days

Construction Completed

May 2013

Project Specs

~12.61 miles (66,000 LF) of canal repair

High-performance turf reinforcement mat installation